09022 Scour Protection Works

Project Analysis

project21Client: Whangarei District Council
Engineer: Derek Bon
Value: $100k
Location: Whangarie, Northland
Contractors Representative: Jeremy Rintoul
Project Manager: Ken Rintoul
Site Supervisor: Alvin Thomson
Construction Programme: 7/12/09 to 22/03/10 (12 weeks)
Justifiable Delays: 22 working days
Completion Date: 26 April 2010

 

Project Brief:

This contract involved the construction of various types of scour protection works in and along a number of river banks in the Whangarei catchment. Such works included gabion baskets, rock spall retaining, hessian bags and a significant amount of debris removal.