09025 Connell Road Bridge A87 Upgrade

Project Analysis

project1Client: Whangarei District Council
Engineer: Derek Bon
Value: $236k
Location: Waipu, Northland
Contractors Representative: Jeremy Rintoul
Project Manager: Myles Gordon
Site Supervisor: David Job
Construction Programme: 10/05/10 to 24/08/10
(16 weeks)
Extensions of Time: 42 working days
Completion Date: 19 October 2010

 

Project Brief:

This contract required the replacement of the sub-structure of an existing steel I beam bridge. The piers and abutments were increased in size, with piling undertaken whilst the bridge remained open to the public. New end spans were fabricated and installed and significant repair works was also undertaken on the existing steel beams, deck and handrails. To complete this contract the pavement approaches were raised and chip sealed.