LRR-01 Leigh Recreational Reserve Visitors Carpark

project8Project Analysis

Client: Department of Conservation
Engineer: Myles Taylor
Value: $356k
Location: Leigh, Rodney
Contractors Representative: Jeremy Rintoul
Project Manager: Myles Gordon
Site Supervisor: David Job
Construction Programme: 28/09/09 to 19/02/10
(16 weeks)
Justifiable Delays: 80 working days
Completion Date: 4 June 2010

 

Project Brief:

This contract involved the construction of an 88 space carpark at the Goat Island Marine Reserve. Construction was undertaken on a green field site within 500m of the marine reserve. Consequently Environmental and Health and Safety compliance requirements were very high with continuous monitoring of waterways and an extensive stromwater management system.