614 Central Areas Slip Repair Package Seven

Project Analysis

project16Client: Kaipara District Council
Engineer: Stuart Kain
Value: $312k
Location: Paparoa, Northland
Contractors Representative: Jeremy Rintoul
Project Manager: Myles Gordon
Site Supervisor: Clint Goldie
Construction Programme: 11/01/10 to 22/03/10
(10 weeks)
Justifiable Delays: 32 working days
Completion Date: 28 May 2010

 

Project Brief:

This contract involved the construction of eighty metres of reinforced concrete retaining wall on three different sites requiring slip rehabilitation. A total of seven hundred and seventy metres of 600mm dia. reinforced pile was constructed. Drilling in blue rock in excess of 40MPa was encountered on a number of pile holes.