7/10/186 Package 2 Flood Damage Slip Repairs

Project Analysis

project13Client: Far North District Council
Engineer: Martin Le Heron
Value: $635k
Location: Hokianga, Northland
Contractors Representative: Jeremy Rintoul
Project Manager: Ken Rintoul
Site Supervisor: Philip Young
Construction Programme: 18/01 – 21/06
& 16/08 -22/10
Justifiable Delays: 13 working days
Completion Date: 22 October 2010

 

Project Brief:

This contract involved the rehabilitation of four slip sites throughout the Far North District using extensive rock spalling, MSE retaining and tied back timber pole walls. A total of 3,000m³ of rock spalls, 5,500m³ of MSE retaining and twenty five metres of timber pole retaining was installed respectively. In addition timber planking, subsoiling and pavement construction were also required.