7/10/187 Package 3 Flood Damage Slip Repairs

Project Analysis

project15Client: Far North District Council
Engineer: Paul Wilson
Value: $308k
Location: Awaroa, Northland
Contractors Representative: Jeremy Rintoul
Project Manager: Ken Rintoul
Site Supervisor: David Job
Construction Programme: 9/10/08 to 26/02/09
(16 weeks)
Justifiable Delays: 61 working days
Completion Date: 27 July 10

 

Project Brief:

This contract requires the replacement of an existing timber railway bridge with a new concrete precast bridge. The new bridge spanned eighteen metres across a tidal river and as part of the contract the installation was to be completed whilst the old bridge was left in place and the railway line was fully operational. This contract involved extensive temporary works construction, piling to twenty eight metres, abutment construction and bridge span installation.